Hey Guys 

Hope you all doing well. Hopefully someone can help me out with a question i have about my new batteries. I have 3 UP5000 batteries connected to a Kodak MKSIII. iv left the setting on the inverter as Pylontech batteries so the BMS is controlling all the figures. Was a little skeptical to play with any settings as the batteries are a little pricey.

Now the bulk and  float charge is set to 53.2 back to discharge at 54. It seems like the batteries always charge up to 50.5 then they show full. It has never gone up to 53.2. The available amp hours also show as 298 and should be 300 at full. I know its just a small amount just wondering if the setting are all correct?

 

thanks in advance 

  • 2 months later...

Hi Thomasel.

If the comms is working between the batteries and the inverter the BMS will tell the inverter what it wants.

On my system I can change setting but it will revert back to what the batteries want.

You can just set the back to grid voltage so that it doesn't take your batteries to low.

I will recommend getting Solar Assistant to allow you to select the lowest State of charge when going back to grid.

I will also allow you to monitor your system remotely and make changes if need be.

And the DLL's....

I got mine working last year and cant remember the steps but if you search the forum you will find the cable specs, config steps etc.

Also download Putty (Used to  serial/ssh/telnet to the batteries and then use CLI to interrogate them..

pwrsys
info
soh 
stat
bat
pwr

socd
getpwr
 

BatteryView_3.0.23_dll.zip

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

Power Forum. Need Help? Please feel free to contact: Power(AT)powerforum.co.za