November 20, 20232 yr I have 2 5kw Deye inverters connected as main and slave. i have hybrid system and grid is coming from 2 different sources. one source of grid is main government electricity and the second source is local generator in area. So at a single time only one is providing electricity, so mainly source 2 is most of the times ON. I need to charge batteries (in some cases) only when government grid is available and not charge batteries from other sources at all. how to configure this knowing that on inverter I have one grid input.