I have sunsynk 5kw inverter and 2 x greenwich 3.6 batteries with total 4.5kw panels. Geyser and oven on non essential loads, so unable to run during load shedding. Usually not an issue however we've had some extended power failures for a few days due to cable theft. I would like to bypass this setup to at least allow me to run the geyser when I need to, seems pity to have no hot water, panels producing loads of power in full sun, batteries at 100% and can't use any of it to run geyser.
Would be an occasional solution when needed as otherwise setup works perfectly in an out of load shedding
Current settings are zero export and priority load.
I was under the impression if i changed to allow export but to limit to load only this would be the solution but no apparently so when there is non concurrent grid input like in a power failure.