Hi, I have a 3 phase generator 35kva (Kipor) with a automatic transfer switch and smart Gen controller.
At the moment I have opted for a single phase 8 KVA Sunsynk inverter which can be expanded to a 3 phase system later ( each inverter doing one phase)
My idea is to rewire my Db board for essential loads on one phase and non essential loads on the other phases for now. Can I use my 3x phase Gen to integrate with my one phase inverter for now. Eg If the batteries run flat the generator will then start to charge the batteries according to % set.
The obvious drawback is that the non essential loads will not have power if there is loadshedding
Any ideas ? Or advise