Hi all,
I am a newbie on this forum so I apologise if I am logging this request on the wrong group / topic.
I have searched the forum but couldn't find a related thread, hence I am posting it on General
I am installing a Solar system which consists of
1 x 8Kw single phase Sunsynk inverter which has 2 x MPPT charge controller's
10 x 450w Pannels (2 strings of 2250w each)
2 x BSL Powerline 5 kWh batteries.
My question is as follows:
Is it better to split the Solar input as to feed one 2550w string into each of the MPPT's or to feed both strings of 4500w into one MPPT and have the 2nd MPPT sit idle. The DC voltages of both options are within spec of the MPPT's