Hi Paull99,
I upgraded my system by adding two Pylontech US2000C batteries to my existing 4X US2000B batteries (Goodwe ES 4.6kW inverter). They are connected as follow:
A1
2000C (Master)
B1
2000B
A2
2000C
B2
2000B
A3
2000B
B3
2000B
All batteries connected in parallel and group A and B connected in parallel on a busbar at the DC Breaker.
Before adding the two C’s, the BMS and CT Meter worked fine. However, after the upgrade the PV Master reports a CT and BMS communication failure. As per the Goodwe Flyer, I disconnected Pin 2 and then only connected pins 4&5, but this problem persist.
Any ideas?
Thank you