September 29, 20223 yr Hello Hoping to pick some brains. With regards to the 12kw 3phase Sunsynk or Deye, is it possible to have only one of the phases use the battery capacity when loadshedding, i.e run the house through the inverter (3 phase house) and then have the essentials on one phase which would then be on the phase in which the battery supplies only ? This may sound silly but the way this house is done I have to tie in on the main cable so if I used a single phase inverter then I would not be able to have 3 phase to run a 3 phase Aircon ever, even when grid is there.
September 30, 20223 yr It is possible to have essentials only on the one phase, yes. It has 3 CTs, you can have 3phases supplied with PV+Battery when grid is available. Though you might not gain that much going with the 3phase vs the single phase 8kW in this case. The 12kW 3 phase can supply up to 6kW on a single phase.