Steve87 Posted December 6, 2023 Share Posted December 6, 2023 Logistical intensive installation on the 1st floor of a 100yrs old building. Only a 50kW backup power solution but with a lot of room for expansion. First of all the HPS50 weighs 610kg & most of that weight is concentrated in the large transformer. The transformer comes in at 550kg. So this was a job that we need to separate the transformer otherwise we could not handle such a massive machine at such a critical weight up a staircase that narrows & turns through 180°. Given the correct tools we accomplished our task. Now for the wiring & for the distribution. Will post more as this unfolds. jumper, TaliaB, zsde and 2 others 5 Quote Link to comment Share on other sites More sharing options...
Steve87 Posted December 6, 2023 Author Share Posted December 6, 2023 The ATESS design team have made one solid industrial grade machine. The magic of pure transformer based design gives me a lot of confidence. jumper, flatfourfan, zsde and 2 others 5 Quote Link to comment Share on other sites More sharing options...
Steve87 Posted December 6, 2023 Author Share Posted December 6, 2023 Now we begin the wiring & also for FreedomWon to dismantle the 40/32 HV for us to move in smaller segments. Jacques Ester, Muttley, flatfourfan and 1 other 4 Quote Link to comment Share on other sites More sharing options...
Steve87 Posted December 15, 2023 Author Share Posted December 15, 2023 She is alive & well, will share our final commission pics in the week. Muttley 1 Quote Link to comment Share on other sites More sharing options...
Steve87 Posted December 15, 2023 Author Share Posted December 15, 2023 Transformer safely fitted back into space, just some distribution work we have to wrap up... Quote Link to comment Share on other sites More sharing options...