Skip to content
View in the app

A better way to browse. Learn more.

Power Forum - Renewable Energy Discussion

A full-screen app on your home screen with push notifications, badges and more.

To install this app on iOS and iPadOS
  1. Tap the Share icon in Safari
  2. Scroll the menu and tap Add to Home Screen.
  3. Tap Add in the top-right corner.
To install this app on Android
  1. Tap the 3-dot menu (⋮) in the top-right corner of the browser.
  2. Tap Add to Home screen or Install app.
  3. Confirm by tapping Install.

Adding panels - system advice

Featured Replies

Hi All,

 

I want to add more panels to my system, currently i have 6 x 400W panels on my Axpert King, I would ideally have liked to add another 6, though that theoretically puts me over the maximum input W to the MPPT. Though i have never seen 2400W from my existing panels.

 

Would it be safe to add another 6 panels considering losses and efficiency or should i play it safe with 4?

Also the position of the new panels will be closer on the roof to the inverter than the existing panels by probably 5 meters or so, do the cable lengths of all strings need to be the same or are differing lengths fine? i assume it doesnt matter but want to be sure when they put it in.

TIA

  • Author

looking deeper into this

 

the panels are 47.0 V and 10.82 A, the inverters mppt is 60-115V and 80Amp max.

the reason i initially went for strings of 2 was that i thought 3 in a string was pushing the Voltage range limit.

 

so 6 strings of (47V*2) 94V at 10.82A a string gives a total amperage of 64.92A. Seems safe?

4 hours ago, Dex_ said:

so 6 strings of (47V*2) 94V at 10.82A a string gives a total amperage of 64.92A. Seems safe?

One point to look out for is protection, are they installing breakers or fuses for each new string. I would assume 15A fuse or breaker per string on a 10.82A circuit. This might also mean upgrading your breaker depending on your setup, feeding PV to inverter as this can now go up to 64A.

  • Author
7 hours ago, Gerrie said:

One point to look out for is protection, are they installing breakers or fuses for each new string. I would assume 15A fuse or breaker per string on a 10.82A circuit. This might also mean upgrading your breaker depending on your setup, feeding PV to inverter as this can now go up to 64A.

I have a 6 input combiner box with type 2 protection, i am not sure of the exact fuses per string off hand or the main fuse, i will need to check that, when it was origionally sourced the requirement to add more panels was discussed so i hope it is in place, will check. 

 

Edited by Dex_

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

Account

Navigation

Search

Search

Configure browser push notifications

Chrome (Android)
  1. Tap the lock icon next to the address bar.
  2. Tap Permissions → Notifications.
  3. Adjust your preference.
Chrome (Desktop)
  1. Click the padlock icon in the address bar.
  2. Select Site settings.
  3. Find Notifications and adjust your preference.