January 18, 20251 yr I'm busy with a parallel installation with two of these - so far just connected to the batteries via a bus bar. Communiaction and current sharing cables not installed yet and PAL setting not activated. Voltage reading at terminals for both inverters are 52.6 V via a multimeter, but one inverter reads 53.0 V and the other 52.1 V. I'm suspecting that this will cause an issue once I activate the parallel settings. Anyone have guidance for calibrating these inverters - the manual seems to refer to such a possibilty. Much appreciated in advance!
January 20, 20251 yr These instructions need cleaning up, but all the information is there: https://forums.aeva.asn.au/viewtopic.php?p=71631#p71631 Being MAX models, you will need the ATE1 command. Use the communications tool.
January 20, 20251 yr 3 hours ago, Shadders said: I shared the SOP I wrote up using the information linked above Hey, neat! I have linked your file at the top of the calibration post. Thanks for doing that; it was sorely in need of a clean up.
February 2, 20251 yr Author Thank you @Coulomb and @Shadders. Can confirm that this works on my Kodak 7.2 kW by following Shadders PDF and using the communication tool link in the same doc.
Join the conversation
You can post now and register later. If you have an account, sign in now to post with your account.